Report type – Timeliness by code table

The Timeliness by code table report provides a more detailed report on timeliness of provision of responses than the Target date by Code table report. This report summarises the timeliness with which questions are closed, by:
Original target date met – which means that the response was provided within the Target response date, and the Target date was not ever adjusted .
Original target date missed – which means that the response was NOT provided within the Target response date, and the Target date was not ever adjusted .
Revised target date met – which means that the response was provided within a Target date that was adjusted at some time during the life of the question.
Revised target date missed – which means that the response was NOT provided within a Target date that was adjusted at some time during the life of the question.